Southern Nevada — GridLiance West Core Transmission Upgrades
GridLiance West, a subsidiary of NextEra Energy Transmission, has started construction on the Core Upgrades Project in Clark and Nye counties, Nevada.
The project includes approximately 155 miles of new or rebuilt 230-kV and 500-kV transmission lines together with new and upgraded substations. The upgrades are designed to add roughly 1 GW of transmission capacity, improve reliability and support further industrial and economic development.
GridLiance expects approximately 500 construction jobs. Completion is targeted for mid-2028.
Status: Construction started September 2026.
Completion: Mid-2028.
Source: NextEra Energy Transmission / GridLiance West, September 9, 2026.