New Texas regulatory filings for KDC’s Project Eagle campus in Plano detail a substantial planned office development associated with AT&T’s headquarters relocation.
The filings, as reviewed by the Dallas Business Journal, cover eight buildings, three parking garages and a utility plant with estimated construction costs of approximately $1.06 billion. Preliminary dates indicate a December 2026 start and March 2029 completion, subject to change.
The records provide fresh scope and schedule detail for a major North Texas corporate campus project.