Skanska secures two contracts worth over $300M

ConDig (06-30–25)  Swedish developer and contractor Skanska has secured an additional contract worth $250 million to upgrade Logan Airport’s Terminal E in Boston.

Under the deal with Massachusetts Port Authority (Massport), the contractor will build a greater than 67,400 square meter (725,000 sq. feet) Terminal E Parking Garage in the existing location. The multi-story structure will feature approximately 4,000 parking spaces, including spaces for ground transportation on the lower level.

The project will also involve the construction of a vehicular bridge connection to the existing central parking complex, as well as a pedestrian bridge connecting the garage to the terminals. In addition, modifications will be made to Arrival and Departures level roadways to accommodate access to the garage.

Solar PV panels will be installed to offset electricity consumption, and the project will seek a Parksmart certification issued by the Green Building Certification Institute, according to the company.

Work will begin in the second quarter and the garage is scheduled to be completed in 2030.

Skanska also bagged an additional contract for an elementary school in Parrish, Florida, for $51 million.

The project involves the construction of the 12,500 square meter (134,600 square feet) elementary school on the 20-acre greenfield site, located along Buckeye Road in Parrish. 

The two-story elementary school includes 63 individual classrooms to accommodate over 950 students in grades K-5. The campus will also feature a covered playground area and a boardwalk that extends to the wetlands.

Work is underway, with an expected completion in the third quarter of 2026.